  • Phase II - Week 5

    Sunday, January 20, 2013

    Week five begins with more progress clearing out the basement space, as well as installing new plumbing in the floors for the mechanical spaces:

  • Phase II - Week 4

    Saturday, January 12, 2013

    As week four begins, electrical conduit work is almost complete:

    Construction 2013-01-12 004

  • Phase II - Week 3

    Saturday, January 5, 2013

    Week three begins with installation of electrical conduit in the back lot to provide new electrical service:

    Construction 2013-01-05 003

  • Phase II - Week 2

    Sunday, December 30, 2012

    As week two begins, radiator removal is well under way.  I'm just glad I don't have to move those at all:

    Construction 2012-12-30 025

  • Phase II Begins - Week 1

    Sunday, December 23, 2012

    With move-out of the chapter house completed on Monday, December 17th, Cheever was officially handed the keys for Phase II.  From the outside it doesn't look like much has happened in a week, but progress is definitely moving along.

  • Fall 2012 Campaign Update

    Thursday, September 27, 2012

    Check your mailboxes! Our initial campaign update for fall 2012 is being mailed beginning today. If you can't wait, you can read it here: Campaign Update - Fall 2012.

  • Phase I Ends - Week 8

    Friday, August 17, 2012

    With week eight the new concrete floor has been poured in the former crawl space, and Phase I officially comes to an end:

    IMG_0370

  • Phase I - Week 7

    Tuesday, August 14, 2012

    Week seven and Phase I is wrapping up. The foundation work is finished and has been backfilled:

    IMG_0349

  • Phase I - Week 6

    Sunday, August 5, 2012

    Sorry, no pictures from week five but week six brings plenty of changes. First up, the pad for the new transformer has been poured on the lot line between us and Theta Xi:

    IMG_0293

  • Phase I - Week 4

    Tuesday, July 24, 2012

    Sorry, no pictures from week three, but week four shows the new foundation walls formed and poured:

    IMG_0258