Week 11 brings a lot of progress from the plumbing and mechanical contractors. Rough plumbing in the new kitchen is largely finished, with mechanical starting next:


Plumbing work continues on the new second floor bathroom:

Prep work indicates the masons will be arriving soon to begin patching existing holes:


Up on second and third floors, ceiling grid is being installed to support the new drywall ceilings:


Also, red conduit indicates that new life safety systems are being installed: